Social Rented Housing: Construction

(asked on 14th October 2025) - View Source

Question to the Ministry of Housing, Communities and Local Government:

To ask the Secretary of State for Housing, Communities and Local Government, if he will encourage the Building Safety Regulator to provide a timeline for decision on the 338 social homes intended for the former Bermondsey Biscuit Factory development site.


Answered by
Samantha Dixon Portrait
Samantha Dixon
Parliamentary Under-Secretary (Housing, Communities and Local Government)
This question was answered on 21st October 2025

The Building Safety Regulator has received three Building Control Applications for new higher risk buildings to be built on the Biscuit Factory site. Progress on each application is set out in the following table. Please note that assessment of applications is a dynamic process, and timetables can change dependent on the information provided by the applicant:

Application Name

Application Number

Current status

Number of homes

When decision is expected

Block OPQ

BCA03545Z1N7

Statutory fire consultation has completed.  Final stages of assessment underway

187 over 14 floors

November 2025

Block W

BCA04254L1T8

Assessment is continuing. Statutory fire consultation will start once all fire matters within the application have been resolved

69 over 18 floors

January 2026

Block V

BCA05762F2G7

Assessment is continuing. Statutory fire consultation will start once all fire matters within the application have been resolved

82 over 10 floors

January 2026