Question to the Ministry of Justice:
To ask the Secretary of State for Justice, pursuant to the answer of 20th October 2025, to question 79734 on Prison Accommodation: Procurement, which projects previously supplied by ISG have now been taken over.
Pursuant to the answer of 20 October 2025 to Question 79734, new replacement contractors have been appointed on all the projects previously supplied by ISG and ESS across the Houseblocks and Refurbishments and Category D Expansion Programmes in line with contingency plans.
Work is underway to enable us to recommence delivery across these projects. We are committed to delivering an additional 14,000 prison places and are on track to do so by 2031, with places fully operational by 2032. We have already delivered c.2,600 of these since taking office.