Trident Submarines: Procurement

(asked on 9th January 2024) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what recent estimate he has made of the cost of replacing each Vanguard class submarine under the Trident nuclear programme.


Answered by
James Cartlidge Portrait
James Cartlidge
Minister of State (Ministry of Defence)
This question was answered on 15th January 2024

Replacing the Vanguard Class, the Dreadnought submarine programme remains on track to deliver to schedule and within the original £31 billion plus £10 billion contingency budget made in the Strategic Defence and Security Review 2015.