Question to the Ministry of Defence:
To ask the Secretary of State for Defence, pursuant to the answer of 19 November 2025 to question 89765 on Military Aircraft: Procurement, what the in-year saving made by cancelling the Shadow Mk2 upgrade programme was.
The decision to cancel the Shadow Mk2 upgrade programme was driven by delays in delivering the required capability and an assessment of increased costs for uncontracted work. As a result, no direct in-year savings were realised from this decision. However, allocated sustainment funding continues to support the operational output of the existing Shadow R Mk1 fleet.