Question to the Ministry of Defence:
To ask the Secretary of State for Defence, with reference to his Department's press release entitled Storage facility for over 900 vehicles completed at MOD Ashchurch, published on 5 March 2025, when all 13 new buildings will be delivered as part of the Vehicle Storage and Support Programme.
The Vehicle Storage and Support Programme (VSSP) remains on schedule and work at MOD Ashchurch will be completed in 2027.
Demolition of all 58 existing buildings as part of the VSSP, has been completed.