Question to the Ministry of Defence:
To ask His Majesty's Government what estimate they have made of the value of the supply chain of the contract for the vessels being constructed for the Defence Marine Services Next Generation Contracts.
The Vessel Replacement Programme within the Defence Marine Services Next Generation In-Port Services contract represents approximately £200 million, 22% of the total In-Port Services contract value. Serco, as the prime contractor, is responsible for managing its supply chain and made the decision to sub-contract to Damen Shipyards Group. The Ministry of Defence monitors prime contractor reporting to ensure compliance with contractual obligations and value-for-money principles.