Wind Power: East Anglia

(asked on 25th January 2023) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask His Majesty's Government why, in contrast to other regions, the Holistic Network Design impact criteria are not being used to assess the suitability of sites for offshore wind power infrastructure in East Anglia.


Answered by
Lord Callanan Portrait
Lord Callanan
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 8th February 2023

The Holistic Network Design (HND) was published in July 2022. For offshore wind projects that do not yet have firm connection contracts, the HND recommends network solutions that deliver coordination, cost and efficiency benefits and an overall reduction in new infrastructure. However it cannot mandate changes to projects with pre-existing connection contracts, including many in East Anglia. For these, the Government has launched the £100m capital grant scheme to support the development of voluntary coordination options.

Reticulating Splines