Question to the Ministry of Defence:

To ask Her Majesty’s Government what the cost has been to date of all Typhoon Force-related works at RAF Lossiemouth; and what is the most recent estimate of the total cost of facilitating the future operation of the Typhoon Force and the Northern Quick Reaction Alert facility at that base.


Answered by
Earl Howe Portrait
Earl Howe
Shadow Deputy Leader of the House of Lords
This question was answered on 20th April 2016

£80.6 million has been committed and will be spent on Typhoon-related works at RAF Lossiemouth. The total cost of facilitating the future operation of the Typhoon Force and the Northern Quick Reaction Alert facility at that base is still being reviewed following the Strategic Defence and Security Review 2015 announcements.