Question to the Ministry of Defence:
To ask the Secretary of State for Defence, for what reason his Department has estimated that the Mechanised Infantry Vehicle programme has a total cost variation to completion of £543 million.
The total cost variation to completion of £543 million in the Mechanised Infantry programme reflects the Defence Command Plan intent to significantly increase the programme scope by enhancing and uplifting the fleet sizes by an initial 100 vehicles.