Radioactive Waste: Dalgety Bay

(asked on 13th May 2021) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, with reference to the Answer of 15 April 2019 to Question 241447 on Radioactive Waste: Dalgety Bay, whether the first stage of the remediations has been completed; and whether the second stage remains on target to be completed in 2021.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 18th May 2021

The first stage of the remediation work has not been completed; however work is underway on the site, following the granting of a licence by the Scottish Environmental Protection Agency, which was granted on 17 May 2021.

The target remains to complete all work by September 2022.