Nuclear Reactors

(asked on 30th November 2017) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, when the PWR3 nuclear reactor programme will move into its manufacturing phase.


Answered by
Harriett Baldwin Portrait
Harriett Baldwin
Shadow Minister (Business and Trade)
This question was answered on 7th December 2017

The Pressurised Water Reactor 3 (PWR3) plant moved into the manufacturing phase in September 2016, following approval for Dreadnought's Delivery Phase 1.