Question to the Ministry of Defence:
To ask the Secretary of State for Defence, pursuant to the Answer of 21 December 2022 to Question 109427 on Ajax Vehicles: Testing, whether Ajax has to undergo any further trials after a successful completion of Reliability and Growth trials in order to reach initial operating capability.
Ajax Initial Operating Capability is not dependent on the completion of the Reliability Growth Trials. However, findings from wider Validation and Verification testing will demonstrate the vehicle’s compliance with system requirements and vehicle readiness for Initial Operating Capability.