Question to the Ministry of Defence:
To ask the Secretary of State for Defence, when he expects project PEGASUS to be completed.
The existing approved cost of Project PEGASUS is £634 million. Following a pause to reassess the requirements for the project, it will now run in two phases. Firstly, the delivery of the store capability, which is due to complete by June 2025. The second stage will be the manufacturing capability, and an assessment phase is underway to determine the best value for money solution with a target for delivery of the first unit in 2030.