To ask the Secretary of State for Defence, what his Department's planned timescale is for agreeing the full business case for the E-7 Wedgetail programme.


Answered by
James Cartlidge Portrait
James Cartlidge
Shadow Secretary of State for Defence
This question was answered on 14th March 2024

The Wedgetail Full Business Case is planned for submission in March 2024, and an approval is expected from the Ministry of Defence in late 2024. The Wedgetail aircraft will commence flying for early stages of testing in 2024, with delivery into service with the RAF in autumn 2025.