Type 23 Frigates

(asked on 14th July 2023) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, if he will list each refit of the Type 23 frigate class over the last ten years by (a) name of ship, (b) contractor carrying out the refit, (c) estimated time to complete the retrofit and (d) actual time to complete the retrofit.


Answered by
James Cartlidge Portrait
James Cartlidge
Minister of State (Ministry of Defence)
This question was answered on 20th July 2023

The requested information is provided in the table below.

Details of the planned duration of each refit period before work commenced could be provided only at a disproportionate cost. The data required would have to be collated from a number of sources, some of which are no longer readily accessible. In addition, some of the data required remains commercially sensitive.

It should be noted that the duration of any refit period is highly dependent on multiple factors including the planned scope of the work, shaped by the age and operating profile of the vessel; the extent of emergent work, which cannot be forecast before the refit commences; and by external factors such as Covid shutdowns.

Ship

Contractor

Start

End

Duration (Months)

HMS PORTLAND

Babcock

Nov-11

May-13

19

HMS IRON DUKE

BAE Systems

Feb-12

Nov-13

22

HMS SOMERSET

Babcock

Apr-12

Mar-13

12

HMS SUTHERLAND

Babcock

Oct-13

Jun-15

21

HMS ST ALBANS

BAE Systems

Apr-13

Aug-14

17

HMS WESTMINSTER

BAE Systems

Oct-14

Mar-17

30

HMS MONMOUTH

Babcock

Jan-14

Sep-15

21

HMS MONTROSE

Babcock

Mar-14

Jul-15

17

HMS ARGYLL

Babcock

May-15

Apr-17

24

HMS NORTHUMBERLAND

Babcock

May-16

Apr-18

23

HMS KENT

Babcock

Oct-16

Oct-18

25

HMS LANCASTER

Babcock

May-17

May-20

36

HMS RICHMOND

Babcock

Sep-17

Mar-20

30

HMS SOMERSET

Babcock

Oct-18

May-22

43

HMS PORTLAND

Babcock

Apr-18

May-21

37

HMS IRON DUKE

Babcock

May-19

Jun-23

49