Guided Weapons: Procurement

(asked on 13th October 2023) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what the projected whole life costs of Marlet (a) were originally and (b) are as of 13 October 2023.


Answered by
James Cartlidge Portrait
James Cartlidge
Shadow Secretary of State for Defence
This question was answered on 23rd October 2023

The original Martlet business case from 2013 provided a cost of £311 million for the demonstration and manufacture phases of the project. The current forecast is £433 million which includes helicopter integration, ship modification and training solution costs shared with the associated Sea Venom project. Through life support cost estimates are commercially sensitive.