Question to the Ministry of Defence:
To ask the Secretary of State for Defence, whether the outturn budget for the Type 31e programme is maintained at £1.25 billion for five ships.
As announced in the National Shipbuilding Strategy, we want five ships at an average price of £250 million per ship. In common with all procurement projects the overall Type 31e programme cost will be determined at the main investment decision point.