Question to the Department for Transport:
To ask the Secretary of State for Transport, how many jobs will be created by HS2 in (a) Northwich, (b) Cheshire and (c) the North of England.
Labour market forecasts can be found in the 'HS2 labour and skills demand and supply forecasting and analysis' published in July 2021.
https://assets.hs2.org.uk/wp-content/uploads/2021/08/HS2_LSF-report_clean_V2-0508.pdf
Whilst we cannot provide geographical specific forecasts, section 2.7 (page 36 - 45) details the labour forecast for building Phase 2bWL, which will all be based in the North West. It estimates there will be a peak workforce of 17,500 in 2029/30, with the workforce sustained at over 14,000 between 2027/28 and 2029/30.
The forecasts for Phase 2a are also given in the table on page 21.