Clyde Naval Base

(asked on 16th March 2020) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, pursuant to the Answer of 12 March 2020 to Question 26968, what the (a) overall budget, (b) current spend and (c) percentage of completion is of each of the 14 projects at HM Naval Base Clyde.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 23rd March 2020

The overall budget allocated to HM Naval Base Clyde projects is £1.6billion, the current spend as of the

29 February 2020 is £329million. The percentage of completion of each of the 14 projects is provided in the

table below:

Project Name

Complete

Single Living Accommodation T2

100%

Submarine Escape Rescue Abandonment and Survival

100%

Neptune Remedial Works

95%

Nuclear Support Hub

70%

Trident Training Facility (Faslane)

70%

Surveillance and Intruder Detection Security Systems

60%

Clyde Programme Requirements

30%

Trident Special Area

25%

Faslane Nuclear Infrastructure Continuous Availability Project

15%

Submarine Training Facility

15%

Coulport Continuous Availability Project

5%

Jetty Facility Security Systems

1%

Single Living Accommodation T3

0%*

Submarine Support Hub

0%*

*Projects with no progress are scheduled to begin in later years of the programme