To ask the Secretary of State for Defence, pursuant to the Answer of 10 March 2025 to Question 34636 on HMS Northumberland: Decommissioning, what the target date is for the delivery of the fleet solid support ships.


Answered by
Maria Eagle Portrait
Maria Eagle
This question was answered on 17th March 2025

Each of the Ships Programmes are progressing.

All of the Type 26 Ships are expected to enter service between 2028 and 2035. The five Type 31 ships are planned to be in service by the early 2030s and the three Fleet Solid Support Ships by 2032.

The Multi-Role Strike Ship programme continues to progress through the Concept Phase. The Outline Business Case is due for submission mid-2025 which will detail the schedule for future contract award milestones.