Question to the Ministry of Defence:
To ask the Secretary of State for Defence, pursuant to the Answer of 7 April 2025 to Question 43178 on Defence: Procurement, how much has been spent on Submarine Disposal Capability; and when the business case was first submitted.
As of April 2025, the Submarine Disposal Capability Project has spent £300,000. The Project submitted its business case to His Majesty’s Treasury in February 2025.