To ask the Secretary of State for Defence, what is the (a) original and (b) current cost expectations for the FDIS programme.
The Future Defence Infrastructure Services (FDIS) Initial Gate Business Case dated 1 March 2018 estimated that the core contracts would cost £3.056 billion over seven years. The current cost expectation for the FDIS contracts is £2.902 billion over seven years.