Southern: Standards

(asked on 3rd July 2018) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government what estimate they have made of how many passengers suffered delays and cancellations across the Southern railway network as a result of service failures on 2 July.


Answered by
Baroness Sugg Portrait
Baroness Sugg
This question was answered on 17th July 2018

The Department for Transport does not make estimates of how many passengers are impacted by delays and cancellations.

Govia Thameslink Railway (which runs Southern services) has reported that, on Monday 2 July, 68% of Southern services arrived at their destination within five minutes of the schedule. A major cause of service disruption was a multiple signal failure between Wivelsfield and Hassocks.